REVTERRA Dashboard

REVTERRA Engineering Dashboard

Friday, February 27, 2026W9
Overall Progress
38%
Completed This Week
18
tasks done
In Progress
26
active tasks
Overdue
14
need attention
Team — Active Tasks
Narendra
  • ITFA-27 Windage Losses Active
  • S40MF-23 Thermal Analysis Overdue
  • ITFB-24 Alternating stress analysis on the bolts holding the top shaft to the top disc of the stacked design Active
  • ITFB-36 Revalidate Torque Ramp Rate Overdue
  • S40MF-3 S40 Simulation Review Overdue
  • ITFB-39 Thermal Analysis Overdue
  • S40MF-25 Material Req. Analysis Overdue
  • ITFA-52 Explicit Dynamics Analysis for containment Active
+3 more
Completed this week (2)
  • Done ITFA-26 Fracture Toughness Calculation
  • Done ITFA-16 Resonance Model testing
Gandhar
  • ITFB-3 ITF Rotor V1 Final Drawing Release Overdue
  • ITFB-38 Magnetic Coupler Design Active
  • ITFB-40 Sensor Mounts Active
  • ITFB-55 Velicon Mounting Part Design Active
  • ITFB-56 ITF Lids Final Drawing Release Active
  • ITFA-55 Vacuum sleeve 3D printing Active
  • ITFB-42 Bearing Design Report Active
  • ITFB-48 Bearing Procurement Active
+1 more
Completed this week (6)
  • Done ITFA-59 Design tapped hole on side of bottom and top lid
  • Done ITFA-57 Mag Coupler Shaft Collar
  • Done ITFA-56 Design and fabricate coupler adapter for 3600 RPM motor
  • Done ITFA-45 Bearing Capsules
+2 more
Curtis
  • ITFA-49 Mag Coupler Shaft Collar Active
  • ITFA-35 Out Containment Ring Size fitting Active
  • ITFA-34 inner Containment Ring Active
  • ITFA-14 Part Received QA Active
  • ITFA-22 Notch Fabrication in Flywheel Active
  • ITFB-57 New PEEK vacuum sleeve fabrication Active
  • ITFB-54 Velicon Mounting Parts Fab Open
Completed this week (3)
  • Done ITFA-54 Send vacuum sleeve drawing to machinist for quotation
  • Done ITFA-39 Motor Cylinder
  • Done ITFA-33 Welding operation
Satyam
  • ITFA-61 I Beam Procurement Active
  • ITFA-60 Top Lid I-Beam Active
  • S40MF-8 Balancing Operation Open
  • S40MF-13 High Torque Mag. Coupler Procurement Open
Completed this week (1)
  • Done ITFA-21 Drawing Release II w/ Notches
Zach
  • ITFA-41 Flywheel alignment Active
  • ITFA-30 Bearing Capsules Refitting Active
  • ITFA-36 Bearing Capsules Fitting Active
  • ITFA-23 Sensor Mounting Active
  • ITFB-29 Create drawing for ITF concrete pad, including anchors to bolt the ITF into, and including space for the Current Power enclosure to sit on Open
  • ITFB-7 ITF Parts Received Open
  • ITFB-12 Initial Motor Spin test - 200 RPM Open
Completed this week (2)
  • Done ITFA-58 Procure Appleton connectors and camlock panels for VFD/motor disconnect
  • Done ITFA-32 Plate Cutting for Spokes
Ben
  • S40MF-22 System IO List Overdue
  • ITFB-41 Final IO list (internal) Active
  • S40MF-12 High Torque Mag. Coupler Design Confirmation Overdue
  • CPSP-28 Follow up: Danfoss IC7 encoder compatibility Active
  • CPSP-36 Follow up: Shipping carrier recommendations from Noah Active
  • CPSP-29 Follow up: Sine wave filter loss and voltage drop Active
  • ITFA-18 Stress Engineering Site Prep for Destructive Test Open
  • S40MF-39 Document motor protection thresholds Open
+4 more
Completed this week (2)
  • Done CPSP-38 Follow up: Basler BE1-FLEX protection relay procurement
  • Done CPSP-37 Follow up: Radiator necessity decision
Attention Needed
ITFA-49 Mag Coupler Shaft Collar Curtis Proske Overdue
ITFA-53 Procure PEEK solid rod for vacuum sleeve Curtis Proske Overdue
S40MF-22 System IO List Ben Jawdat Overdue
ITFA-27 Windage Losses Narendra Gupta Overdue
Needs Scheduling (2)
CPSP-24 Pad Steel Fabrictaion Zach Galvarro
CPSP-25 Pad Concrete Pour Satyam Shukla