REVTERRA Engineering Dashboard
Friday, February 27, 2026
W9
Overall Progress
38%
Completed This Week
18
tasks done
In Progress
26
active tasks
Overdue
14
need attention
Team — Active Tasks
Narendra
ITFA-27
Windage Losses
Active
S40MF-23
Thermal Analysis
Overdue
ITFB-24
Alternating stress analysis on the bolts holding the top shaft to the top disc of the stacked design
Active
ITFB-36
Revalidate Torque Ramp Rate
Overdue
S40MF-3
S40 Simulation Review
Overdue
ITFB-39
Thermal Analysis
Overdue
S40MF-25
Material Req. Analysis
Overdue
ITFA-52
Explicit Dynamics Analysis for containment
Active
+3 more
Completed this week (2)
Done
ITFA-26
Fracture Toughness Calculation
Done
ITFA-16
Resonance Model testing
Gandhar
ITFB-3
ITF Rotor V1 Final Drawing Release
Overdue
ITFB-38
Magnetic Coupler Design
Active
ITFB-40
Sensor Mounts
Active
ITFB-55
Velicon Mounting Part Design
Active
ITFB-56
ITF Lids Final Drawing Release
Active
ITFA-55
Vacuum sleeve 3D printing
Active
ITFB-42
Bearing Design Report
Active
ITFB-48
Bearing Procurement
Active
+1 more
Completed this week (6)
Done
ITFA-59
Design tapped hole on side of bottom and top lid
Done
ITFA-57
Mag Coupler Shaft Collar
Done
ITFA-56
Design and fabricate coupler adapter for 3600 RPM motor
Done
ITFA-45
Bearing Capsules
+2 more
Curtis
ITFA-49
Mag Coupler Shaft Collar
Active
ITFA-35
Out Containment Ring Size fitting
Active
ITFA-34
inner Containment Ring
Active
ITFA-14
Part Received QA
Active
ITFA-22
Notch Fabrication in Flywheel
Active
ITFB-57
New PEEK vacuum sleeve fabrication
Active
ITFB-54
Velicon Mounting Parts Fab
Open
Completed this week (3)
Done
ITFA-54
Send vacuum sleeve drawing to machinist for quotation
Done
ITFA-39
Motor Cylinder
Done
ITFA-33
Welding operation
Satyam
ITFA-61
I Beam Procurement
Active
ITFA-60
Top Lid I-Beam
Active
S40MF-8
Balancing Operation
Open
S40MF-13
High Torque Mag. Coupler Procurement
Open
Completed this week (1)
Done
ITFA-21
Drawing Release II w/ Notches
Zach
ITFA-41
Flywheel alignment
Active
ITFA-30
Bearing Capsules Refitting
Active
ITFA-36
Bearing Capsules Fitting
Active
ITFA-23
Sensor Mounting
Active
ITFB-29
Create drawing for ITF concrete pad, including anchors to bolt the ITF into, and including space for the Current Power enclosure to sit on
Open
ITFB-7
ITF Parts Received
Open
ITFB-12
Initial Motor Spin test - 200 RPM
Open
Completed this week (2)
Done
ITFA-58
Procure Appleton connectors and camlock panels for VFD/motor disconnect
Done
ITFA-32
Plate Cutting for Spokes
Ben
S40MF-22
System IO List
Overdue
ITFB-41
Final IO list (internal)
Active
S40MF-12
High Torque Mag. Coupler Design Confirmation
Overdue
CPSP-28
Follow up: Danfoss IC7 encoder compatibility
Active
CPSP-36
Follow up: Shipping carrier recommendations from Noah
Active
CPSP-29
Follow up: Sine wave filter loss and voltage drop
Active
ITFA-18
Stress Engineering Site Prep for Destructive Test
Open
S40MF-39
Document motor protection thresholds
Open
+4 more
Completed this week (2)
Done
CPSP-38
Follow up: Basler BE1-FLEX protection relay procurement
Done
CPSP-37
Follow up: Radiator necessity decision
Attention Needed
ITFA-49
Mag Coupler Shaft Collar
Curtis Proske
Overdue
ITFA-53
Procure PEEK solid rod for vacuum sleeve
Curtis Proske
Overdue
S40MF-22
System IO List
Ben Jawdat
Overdue
ITFA-27
Windage Losses
Narendra Gupta
Overdue
Needs Scheduling
(2)
CPSP-24
Pad Steel Fabrictaion
Zach Galvarro
CPSP-25
Pad Concrete Pour
Satyam Shukla